Multi-purpose sand-filled pitch

Blakedown were contracted by Marriott Construction to construct a sand-filled multi-sports facility at Cambridge Regional College. The playing surface selected for the MUGA was Edel’s PP 24mm (astroturf) installed onto a 15mm rubber shockpad.

  • Client: Marriott Construction
  • Contract Type: Sub-contract
  • Contract Value: £115,000
  • Build Time: 8 weeks

The project was completed with 3m high perimeter fencing including 1.2m rebound panels, and four floodlighting columns for evening community use.

Location: King's Hedges Road, Cambridge, CB4 2QT