New Playing Fields with SuDS

Blakedown were chosen as contractors for the construction of new playing fields in east Barnet next to the Jewish Community Secondary School (JCoss).

  • Client: London Borough of Barnet
  • Contract Value: £345,000
  • Build Time: 12 weeks

Working for lead designers Conisbee, the job entailed an extenisve cut-and-fill, remodelling of approximately 2,500m3 of soil to form level fields, new rootzone mixed on site and spread, and the installation of a land drainage system linked to cellular attenuation tanks. Blakedown then laid over 10,000m2 of turf to complete the playing fields.

Location: Castlewood Road, New Barnet, EN4 9GE