Blue Acrylic Tarmac Courts

Client: Bicester Lawn Tennis Club

Contract Type: JCT Minor Works

Contract Value: £78,000

Build Time: 6 weeks

Blakedown were contracted through the Sport England 'Inspired Facilites: Places People Play' framework to resurface the tennis courts at Bicester Lawn Tennis Club

The old, worn-out existing tarmac surface was lifted out and a new tarmac layer was installed with a two-tone, blue acrylic coating applied as the playing surface.

The team were utterly professional from start to finish. They offered us complete reassurance throughout the works that we had selected the right people for the job; both in terms of quality and customer service. I would highly recommend Blakedown to everyone.

- Club Chairman