Bedwas High School
3G Rugby Pitch Construction
Blakedown Sport and Play undertook the role of principal contractor for the renovation of a 3G rugby pitch.
Responsibilities included the careful removal of the existing 3G surface and shock pad, followed by necessary repairs and preparation of the tarmac base.
During the installation phase, we implemented a high-quality 20mm shock pad and a top-grade 60mm 3G dual-yarn surface, meeting the stringent standards set by FIFA Quality Pro and World Rugby.
Additionally, Blakedown handled supplementary tasks such as fencing, kickboard installation, combination goal installation, and established a comprehensive maintenance package.
Client: Bedwas High School, Caerphilly
Contract Value: £263,000
Contract Duration: 8 weeks