Trinity High School

3G Pitch Construction

Client:  Trinity High School & Sixth Form Centre

Contract Value:  £337,000

Build Time:  10 weeks

Blakedown Sport and Play were awarded the resurfacing and conversion of a 101.4m x 63m sand-dressed Multi-use pitch to a full-size 3G FIFA Quality football pitch.

The original fencing and kickboards were removed and disposed of offsite, followed by the removal of the existing carpet, which was sent offsite to be recycled by SPORTEX. The original base was cleaned, and topped with TigerTurf Premier Pro Elite 50, football line markings, and sand and SBR infill. Additional works included brand new perimeter fencing and kickboards.